A contractor, Hosier Worldwide, began removing the deck of the bridge on Dec. 27, Thilges said. The Deer River-based ...
A thunderous boom and a large billow of dark-gray smoke rising in the air marked the quick demise of steel beams that had ...
County commissioners last year voted to replace the bridge and remove the nearby Rapidan Dam, both of which were at risk of crumbling after last year's deluge.
A Twin Cities engineering firm hired to design the demise of the Rapidan Dam expects it to disappear by the end of 2028 — 118 years after the structure was completed southwest of Mankato, Minn.
Heavy rain back in June 2024 caused severe flooding that breached the Rapidan Dam on the western side. Erosion around the ...
A subcontractor of the company hired to remove the County Road 9 bridge over the Blue Earth River used explosive charges to ...
Engineers plan to start removal of the Rapidan Dam in 2027, after it failed during major flooding last year. The process of ...
His $887 million pitch includes $10 million for dam recovery efforts after last summer’s catastrophic flooding ...
An engineering firm hired Tuesday to design the demise of the Rapidan Dam expects it to disappear by the end of 2028 — 118 ...
Governor Tim Walz unveiled his proposed 2025 infrastructure plan on Thursday that includes $887 million for projects that ...
FOX 9 Minneapolis-St. Paul on MSN4h
Bridge near Rapidan Dam demolished
Multiple explosions demolished the County Road 9 bridge near the Rapidan Dam after last summer's breach that led to the dam's ...